To give approval to tender the East of Otley Relief Road Scheme following the Council’s success in securing a grant allocation of £6.3m through the government’s Housing Infrastructure Fund and in February 2020, the Executive Board approving the drawdown of £2.245m from the HIF allocation to progress the East of Otley Relief Road to a point where the HIF fund could be claimed.
Decision type: Key
Reason Key: Financial Impact>£500K;
Decision status:
Wards affected: Otley and Yeadon;
Notice of proposed decision first published: 28/10/2020
Decision due: Not before 26th Nov 2020 by Director of City Development
Lead director: Director of City Development
Department: City Development
Contact: Paul Russell, Principal Engineer 0113 378 7259 Email: paul.russell@leeds.gov.uk.
Consultation process
Internal briefings during the completion of the Procurement Plan
Consultees
Executive Member for Climate Change, Transport and Sustainable Development
Officers in Procurement, Legal and Highways and Transportation