Transforming Cities Fund: Holbeck Gateway Phase 1

To approve the detailed design and delivery of Phase 1 of the Holbeck Gateway, being one of the TCF Leeds City Centre Cycling Improvement schemes and comprising:

  The provision of an off carriageway cycle route parallel to A643 Ingram Distributor with upgraded surface, street lighting and wayfinding

Approve expenditure of £600k, to be fully funded by the TCF programme under an existing funding agreement. 

To request the City Solicitor to advertise a package of traffic regulation orders to support the delivery of the scheme, and subject to no objections being received to make and seal the orders as advertised.

Decision type: Key

Reason Key: Financial Impact>£500K;

Decision status:

Wards affected: Beeston and Holbeck;

Notice of proposed decision first published: 25/02/2021

Decision due: Not before 26th Mar 2021 by Director of City Development

Lead director: Director of City Development

Department: City Development

Contact: Christopher Way, Traffic Engineer 0113 378 7493 Email: christopher.way@leeds.gov.uk.

Consultation process

Ward members have been briefed and will be updated.

Executive Member has been briefed on the TCF project and will be updated on this specific proposal.

Public consultation for TCF is active on Your Voice and ran to mid-February.

Consultees

Ward members

Executive Member for Climate Change, Transport and Sustainable Development

Statutory consultees (Police, Fire, Ambulance, WYCA)

Public via Your Voice