A58(M) Woodhouse Tunnel Strengthening Works

Following, and subject to full approval being granted by the Department for Transport,

(i)  Approve the implementation of the A58(M) Woodhouse Tunnel Strengthening Works; and

(ii)  Give authority to incur expenditure of £20 million.

Decision type: Key

Decision status: Recommendations Approved

Wards affected: Burmantofts and Richmond Hill; City and Hunslet; Hyde Park and Woodhouse;

Notice of proposed decision first published: 07/12/2012

Decision due: 8 May 2013 by Executive Board

Lead director: Director of City Development

Department: City Development

Contact: Paul Russell, Principal Engineer Email: paul.russell@leeds.gov.uk, 0113 24 76171 Email: paul.russell@leeds.gov.uk.

Consultation process

On such a key part of the highway network, an extensive consultation programme is being developed.  This will include all ward Members and key stakeholders.  Findings will be included in the Executive Board report.

Portfolio Holder: Portfolio: Development and the Economy