Reference: D44833
Decision Maker: Director of Children and Families
Decision status: For Determination
Is Key decision?: No
Is subject to call in?: No
The Chief Officer Learning Improvement is
requested to:
• Approve the expenditure of £92,005 from capital scheme
number 32457/SOU/HIG for the design and delivery of the off-site
highways and off-site planting works, as conditioned by Planning,
to support the South Leeds SEMH development. This figure includes
the design fees for the work and full delivery cost as well as a
client held contingency commensurate with works of this scale and
risk.
• Authorise acceptance of the cost estimate submitted by
Highways in the sum of £77,004, including all design and
development fees, and approve placement of the necessary
order.
• Authorise acceptance of the cost estimate submitted by Parks
& Countryside in the sum of £3,000, including all design
and development fees, and approve placement of the necessary
order.
• Note the following:
a. That ‘Approval to Spend’ the full SEMH programme
cost of £45m, from capital scheme number 32457/000/000,
required to cover all costs incurred to facilitate this programme
was granted at the 27th July 2016 Executive Board as part of the
“Investment in new Social, Emotional and Mental Health
Specialist Provision for children and young people”
paper.
b. That this constitutes one of three developments to be undertaken
as part of the SEMH programme, each of which will be formalised
under individual scheme specific contracts. A cross programme
budget of £45m has been identified for this of which
£40m has been allocated for post-feasibility work streams and
construction on-site. The particulars within this report refer to
the necessary off-site works at South Leeds only and their
associated design costs. Further Design and Cost Reports will be
submitted referring specifically to the projects at North Leeds
upon completion of the design work by Highways. The works at East
Leeds have been approved under a separate report.
c. The programme dates identified in section 4.0 of this report, in
relation to the implementation of this decision, represents the
critical path for project success and must be adhered to where
possible.
d. The officer responsible for implementation is the Senior Project
Officer.
Wards Affected: Middleton Park;
Contact: Christopher Gosling, Estate Management - Development Officer 0113 3951403 Email: christopher.gosling@leeds.gov.uk.