The Head of Learning Systems agreed to:
· authorise expenditure of £489,417 from capital scheme number 32274/BGE/ALL to enable the installation of additional accommodation, including all necessary ancillary works, at Allerton CofE Primary School;
· authorise acceptance of the tender submitted by the Leeds Local Education Partnership in the sum of £365,204, including all design fees;
· note the programme dates identified in section 4.0 of the attached report in relation to the implementation of this decision. The final delivery date for this scheme is prior to the commencement of term September 2016; and
· note that the officer responsible for implementation is the built Environment Principal Development Officer.