The Chief Officer (Highways and Transportation):
i) gave authority to incur expenditure of £8,459,229 (£5,835,646 works costs and £1,375,657 internal staff and partner design fee costs plus £1,247,926 inspection, assessment and asset management fees) funded from the 2017/18 Local Transport Plan Capital Grant Allocation;
ii) gave authority to incur expenditure of £11,500,000 for planned highways asset maintenance and strengthening (Highways) funded from Leeds City Council Capital Resources (£10,267,856 works costs and £1,232,144 staff fees);
iii) gave authority to incur expenditure of £3,130,000 for planned highways asset maintenance and strengthening (Structures) funded from Leeds City Council Capital Resources (£2,710,000 works costs and £420,000 staff fee costs);
iv) approved the addition of the schemes listed in appendices B and C to this report into the Highways Assets Capital Programme for 2017/18;
v) noted the addition of schemes listed in appendix D to this report into the Highways Assets Planned Revenue Programme for 2017/18; and
iv) The Chief Officer shall be responsible for implementation of the attached programmes of work within the 2017/18 financial year.
The Chief Officer (Highways and Transportation):
i) gave authority to incur expenditure of £8,459,229 (£5,835,646 works costs and £1,375,657 internal staff and partner design fee costs plus £1,247,926 inspection, assessment and asset management fees) funded from the 2017/18 Local Transport Plan Capital Grant Allocation;
ii) gave authority to incur expenditure of £11,500,000 for planned highways asset maintenance and strengthening (Highways) funded from Leeds City Council Capital Resources (£10,267,856 works costs and £1,232,144 staff fees);
iii) gave authority to incur expenditure of £3,130,000 for planned highways asset maintenance and strengthening (Structures) funded from Leeds City Council Capital Resources (£2,710,000 works costs and £420,000 staff fee costs);
iv) approved the addition of the schemes listed in appendices B and C to this report into the Highways Assets Capital Programme for 2017/18;
v) noted the addition of schemes listed in appendix D to this report into the Highways Assets Planned Revenue Programme for 2017/18; and
iv) The Chief Officer shall be responsible for implementation of the attached programmes of work within the 2017/18 financial year.