Issue - decisions

Design & Cost Report & Tender Acceptance for the Learning Places 2017 Bulge Cohort - Immaculate Heart of Mary Catholic Primary School (Phase Two)

Capital Scheme Number: 32450/BGE/IHM

15/09/2017 - Design & Cost Report & Tender Acceptance for the Learning Places 2017 Bulge Cohort - Immaculate Heart of Mary Catholic Primary School (Phase Two)<br/><br/>Capital Scheme Number: 32450/BGE/IHM<br/>

The Head of Learning Systems agreed to:

 

1.  Authorise expenditure of £436,656.36 from capital scheme number 32450/BGE/IHM to allow phase two of the ‘bulge’ cohort works at Immaculate Heart of Mary Catholic Primary School to commence over summer 2017.  This works forms part of the Learning Places 2017 Bulge Cohort Programme.

 

2.  Authorise acceptance of the tender submitted by Immaculate Heart of Mary Catholic Primary School in the sum of £416,238.76 for delivery of phase two.  This figure is inclusive of all fees and costs incurred directly by Immaculate Heart of Mary Catholic Primary School. 

 

3.  Note that the breakdown of project costs, highlighted in point 1 above, are detailed within section 5.5 of this report.

 

4.  Note that this report refers to phase two only, approval for the phase one works is subject to a separate programme and approvals report.

 

5.  Note the programme dates identified in section 4.0 of this report in relation to the implementation of this decision.

 

6.  Note that the officer responsible for implementation is the Head of Learning Systems.