Details of officer decisions relating to planning applications.
To approve a 12 Month contract extension for the supply of fresh fruit and vegetables to Leeds City Council by GT Produce from 1st July to 2016 to 30th June 2017 with an estimated annual value of £750k.
Decision Maker: Deputy Chief Executive
Decision published: 18/08/2015
Effective from: 04/09/2015
Decision:
The Chief Officer approved the award of a 12 month contract extension for the supply of fresh fruit and vegetables to GT Produce Ltd commencing 01 July 2016 to 30 June 2017
Wards affected: (All Wards);
Lead officer: Mandy Snaith
Decision Maker: Director of Children's Services
Decision published: 14/08/2015
Effective from:
Decision:
The Director of Children’s Services
agreed to:
• Note the negotiations held with Solicitors acting on behalf
of the Academy, DfE, Academy Trust and PFI Consortium;
• Give authority for the following Agreements to be executed
and completed to enable the Academy to transfer on the 1st
September 2015:
o Deed of variation;
o LCC License to Assign
o Deed of Novation;
? Commercial Transfer Agreement;
? Principal Agreement; and
? Schools agreement.
• Together with any other documentation required to complete
the transfer; and
• Give authority for any other necessary action to be taken to
effect the transfer.
Wards affected: Middleton Park;
Lead officer: Nigel Wilson
Decision Maker: Director of Children's Services
Decision published: 13/08/2015
Effective from:
Decision:
The Director of Children's Services approved
the waiver of the following contract procedure rule(s):
Contract procedure rules No. 8.1 and 8.2 - Intermediate value
procurements, and award a contract to Wellspring in the sum of
£80,000. The contract shall commence on the 31st August 2015
and expire on 31st August 2016.
Wards affected: (All Wards);
Lead officer: Mary Brittle
Decision Maker: Director of Environment and Housing
Decision published: 13/08/2015
Effective from:
Decision:
The Natural Environment Manager authorised the
declaration of paths at the former Gamblethorpe Tip site as public
rights of way which will result in the addition of six bridleways
and a footpath to the Definitive Map and Statement.
Wards affected: Garforth and Swillington;
Lead officer: Claire Tregembo
Decision Maker: Director of Environment and Housing
Decision published: 13/08/2015
Effective from:
Decision:
Approved the award of an Asbestos survey
contract for 3 years with an extension of one further
year.
Wards affected: (All Wards);
Lead officer: Simeon Perry
To authorise a total of £1.6M framework call-off contracts to 30 community learning providers in academic year 2015/16.
Decision Maker: Director of Children's Services
Decision published: 13/08/2015
Effective from: 29/08/2015
Decision:
The Chief Officer Employment and Skills approved:
· the funding allocations to providers to the total value of £1.5m for the academic year 2015-16 and, authorised the award of year 2 call-off contracts to providers on the three year Community Learning framework 2014-17.
· the amendments to the Learner Fees Policy from September 2015 to raise the learner fee from £2.30 to £3.00 per hour for adults not in receipt of any means tested benefits and, from 0.60p to 0.80p per hour for those in receipt of State Pension.
· an increase in the hourly rate paid to providers for Learning Support Assistants from £7.50 to £8.50 per hour in line with changes in the minimum wage.
Wards affected: (All Wards);
Lead officer: Michelle Anderson
Decision Maker: Director of Adult Social Services
Decision published: 12/08/2015
Effective from:
Decision:
The Director of Adult Social Services approved
the recommendation to incur expenditure of a total of
£165,000 to fund the creation of a community base at Cross
Gates Community Centre on scheme 14997CRO in line with the agreed
programme of works. The proposed timescale for the implementation
of the decision is from October to December 2015. The Project
Manager, Adult Social Care Programme Management Office, is
responsible for implementing the decision.
Wards affected: Killingbeck and Seacroft;
Lead officer: Ivan Barnett
Decision Maker: Director of City Development
Decision published: 12/08/2015
Effective from:
Decision:
The Director of City Development has approved
the terms for the acquisition of the properties to be developed at
the subject site.
Wards affected: Bramley and Stanningley;
Lead officer: Adrian Dean
Decision Maker: Director of City Development
Decision published: 12/08/2015
Effective from:
Decision:
The Director of City Development has approved
the terms for the Waiver of Contract following Contracts Procedure
Rule: 9.1 (High Value Procurements) and allow the Council to enter
into a purchase agreement for the land and 8 no units being
constructed by the current landowner RDF Leeds Ltd on the former
Lord Cardigan Pub site.
Wards affected: Bramley and Stanningley;
Lead officer: Adrian Dean
To accept the Skills Funding Agency contract for Leeds City Council to receive £2.1M funding for community learning in academic year 2015/16.
Decision Maker: Director of Children's Services
Decision published: 11/08/2015
Effective from: 27/08/2015
Decision:
The Director of Children’s Services authorised acceptance of SFA Conditions of Funding (Grant) - 2015 to 2016 to receive £2.1 million SFA funding for Leeds Community Learning and £16k for Adult Skills Budget delivery in the academic year 2015-16.
Wards affected: (All Wards);
Lead officer: Michelle Anderson
The Deputy Chief Executive approves the procurement and implementation of an employee benefit web based platform, and that the Deputy Chief Executive approves the procurement of the salary sacrifice schemes which will bring savings of approx. £630,000 per year to the Local Authority.
Decision Maker: Deputy Chief Executive
Decision published: 10/08/2015
Effective from: 04/09/2015
Decision:
1. Approval of the procurement and implementation of an employee benefit web based platform
2. Approval of the introduction of the salary sacrifice schemes which will bring savings of up to approx. £452,600 per year to the Local Authority.
3 Agreement to use part of the savings generated in 2 to fund the web based platform
Wards affected: (All Wards);
Lead officer: Alex Watson
Decision Maker: Director of City Development
Decision published: 07/08/2015
Effective from:
Decision:
The Head of Engineering Services:
i) noted the highway works as outlined in Section 3.3 and indicated
on drawings WB/RL/003 Rev B and S106 Highway Works Plan attached at
Appendix 1;
ii) gave authority to implement the works as set out in Section
3.3; and
iii) gave authority to incur expenditure of £400,000, being
£330,000 works costs and £70,000 staff costs, all to be
fully funded by the developer from the signed S106 Agreement.
Wards affected: Beeston and Holbeck; Farnley and Wortley;
Lead officer: Michael Norcliffe
Decision Maker: Director of City Development
Decision published: 07/08/2015
Effective from:
Decision:
The Head of Engineering Services:
i) noted the contents of this report;
ii) noted the cost of the additional works as £678,000 which
are to be fully funded by the Developer from a separately held
account;
iii) authorised the injection of £678,000 into the
Council’s capital programme, fully funded by the
Developer;
iv) gave authority to incur expenditure of £678,000 in
delivering these additional works, fully funded by the
Developer.
Wards affected: Bramley and Stanningley; Horsforth; Kirkstall;
Lead officer: Paul Russell
Decision Maker: Assistant Chief Executive (Citizens and Communities)
Decision published: 07/08/2015
Effective from:
Decision:
The Assistant Chief Executive (Citizens and
Communities) has approved the sub-delegation scheme as described in
and set out as Appendix 1 to the attached report.
Lead officer: Beverley Benjamin
Decision Maker: Director of Children's Services
Decision published: 07/08/2015
Effective from:
Decision:
The Area Head of Targeted Services (ENE)
agreed to publish the attached record of decisions made in July
2015
Wards affected: (All Wards);
Lead officer: Ruth Kitson
Decision Maker: City Solicitor
Decision published: 07/08/2015
Effective from:
Decision:
The City Solicitor has approved the
sub-delegation scheme as described in and set out as Appendix 1 to
the attached report.
Lead officer: Clare Millington
Decision Maker: Director of City Development
Decision published: 07/08/2015
Effective from: 23/09/2015
Decision:
The Head of Asset Management has accepted to
list the former Shoulder of Mutton, 31 Potternewton Lane, Chapel
Allerton. Leeds LS7 3LW on the List of Assets of Community Value on
the basis that the nomination satisfactorily meets the criteria
laid down in the Localism Act 2011.
Wards affected: Chapel Allerton;
Lead officer: Catherine Broadhead
Decision Maker: Director of Children's Services
Decision published: 06/08/2015
Effective from:
Decision:
The Director of Children's Services agreed to
waive contrct procedure rule 9.1 and 9.2 and award the contract for
clinical support and supervision to the therapeutic social work
team to Leeds Community Healthcare Trust (LCHT) for 12 months with
a possible further one year extension.
Wards affected: (All Wards);
Lead officer: Louise Atherton
Request to access the Basic Need Programme Capital Risk Fund to enhance the previously agreed budget of £5,758,179 to deal with a price increase from the pre-tender estimate to the actual tender return price. The price increase is expected to be in the region of £600k.
Decision Maker: Director of Children's Services
Decision published: 06/08/2015
Effective from: 22/08/2015
Decision:
The Director of Children’s Services approved an application to the Capital Risk Fund for £797,424 to enhance the previously agreed budget of £1,295,400 and note that the Chief Officer, Projects, Programmes and Procurement Unit is responsible for scheme delivery which will be completed June 2016.
Wards affected: Calverley and Farsley;
Lead officer: Darren Dobson
Decision Maker: Director of City Development
Decision published: 05/08/2015
Effective from:
Decision:
The Head of Engineering Services:
i) authorised the detailed design and implementation of a scheme to
introduce ‘No Waiting At Any Time’ restrictions at the
junction of King Edward Crescent and King Edward Avenue, at the
junction of Broadgate Lane and King Edward Avenue and in
Chaddlewood Close, Horsforth. Details are shown on drawing no:
TM-18-2323-12-01A;
ii) approved the design and implementation of a speed hump and
speed cushions on North Broadgate Lane/ Broadgate Lane and to raise
the existing crossing points of two existing zebra crossing
facility with extending the footway build-outs associated with
them, at the location of North Broadgate Lane/ Broadgate Lane,
Horsforth, at a cost of £42,000. Details are shown on drawing
no: TM-18-2323-12-01A; and
iii) gave authority to display a Notice under the provision of
Section 90c of the Highways Act 1980, to inform members of the
public of traffic calming measures in the form of a speed hump,
raising the existing zebra crossings points and the provision of
speed cushions all on North Broadgate Lane/ Broadgate Lane,
Horsforth.
Requested the City Solicitor to:
a) Advertise a draft Traffic Regulation Order to introduce
‘No Waiting At Any Time’ restrictions at the junction
of King Edward Crescent and King Edward Avenue, at the junction of
Broadgate Lane and King Edward Avenue and in Chaddlewood Close, as
shown on drawing TM-18-2323-12-01A; and if no valid objections are
received, to request that the City Solicitor make, seal and
implement the orders as advertised; and
b) Advertise a notice under Section 90c of the Highways Act 1980 to
provide traffic calming measures in the form of raising the
existing two Zebra crossings points to humped crossings, the
provision of speed cushions and a speed hump on North Broadgate
Lane/ Broadgate Lane, Horsforth.
Wards affected: Horsforth;
Lead officer: Peter Walwyn
Decision Maker: Director of City Development
Decision published: 05/08/2015
Effective from:
Decision:
The Head of Engineering Services:
i) approved, subject to public consultation, the detailed design
and implementation of a scheme to amend some of the existing
traffic calming features on Town Street, Middleton, at an estimated
cost of £18,562;
ii) gave authority to advertise a Notice for the road humps that
conforms with the Highways Act 1980 (90c Notice);
iii) gave authority to incur expenditure of £18,562 to be
funded from the Shape Lane Section 106 private development
receipts.
Wards affected: Middleton Park;
Lead officer: Peter Walwyn
Decision Maker: Director of Environment and Housing
Decision published: 05/08/2015
Effective from:
Decision:
The Chief Officer for Housing Management
agrees to recruit 4 x two year duration, grade (C1) graduate
Project Officers posts within the Housing Leeds, Housing Management
Division.
Post creation to support delivery of projects associated with
implementation of current and future Housing Leeds service
objectives.
Wards affected: (All Wards);
Lead officer: Liz Cook
Decision Maker: Director of City Development
Decision published: 04/08/2015
Effective from:
Decision:
The Chief Officer Culture and Sport has agreed
to waive Contracts Procedure Rule No 3.1.15 (Requirement to use the
Council’s standard tender documents for the procurement of
appoint the following companies to provide vending services) and
8.1 & 8.2 (Intermediate Value Procurements)in order to appoint
the contract for the vending of Sports Nutrition Products to the
Leeds based company ‘Nutrition2Go’.
Wards affected: Various;
Lead officer: Richard Jones
Decision Maker: Director of Children's Services
Decision published: 04/08/2015
Effective from:
Decision:
The Chief Officer, Partnership Development and
Business Support approved the decision to waive contract procedure
rule 8.1 and 8.2 and purchase the two additional modules from
Tribal Services to support the work atound promotion and take-up of
places for eligible 2 year olds.
Wards affected: (All Wards);
Lead officer: Barbara Robinson
To authorise procurement of services for the next phase of delivery of the Council’s Construction Skills Programme.
Decision Maker: Director of Children's Services
Decision published: 04/08/2015
Effective from: 20/08/2015
Decision:
The Director of Children’s Services authorised the procurement of a fixed price contract to a potential maximum value of £483,333 to deliver the Construction Skills Programme from 1 December 2015 to 31 March 2017, including an option to extend the contract for a further two periods of 12 months, subject to funds being available and satisfactory performance by the Contractor.
Wards affected: (All Wards);
Lead officer: Michelle Anderson
Decision Maker: Director of Environment and Housing
Decision published: 03/08/2015
Effective from:
Decision:
The Director, Environment and Housing approved
the request to provide a voluntary grant of £10K per annum
for a three year period covering 2015 to 2018 to Unipol Student
Homes to be used to support initiatives in the private rented
sector.
Wards affected: (All Wards);
Lead officer: Mike Brook
Decision Maker: Director of Environment and Housing
Decision published: 03/08/2015
Effective from:
Decision:
The Chief Officer of Housing Management agreed
to approve the proposal for the partnership agreement with WYCAS to
a value of £8,648.00. In line with the following Contract
Procedure Rule Guidance 7.1
Wards affected: (All Wards);
Lead officer: Ian Montgomery
Decision Maker: Director of City Development
Decision published: 03/08/2015
Effective from:
Decision:
The Director of City Development has reviewed
the decision to add The Old Cock, 11 Crossgate, Otley, LS21 1AA to
the List of Assets of Community Value and agreed that the asset
should remain on the list.
Wards affected: Otley and Yeadon;
Lead officer: Neil Charlesworth
Decision Maker: Director of City Development
Decision published: 03/08/2015
Effective from:
Decision:
The Director of City Development has reviewed
the decision to add Otley Tap House,66 Boroughgate, Otley, LS21 1AE
to the List of Assets of Community Value and agreed that the asset
should remain on the list.
Wards affected: Otley and Yeadon;
Lead officer: Neil Charlesworth
Key decision. The level of funding is in excess of £250,000 for each year of the contract.
Decision Maker: Director of Environment and Housing
Decision published: 31/07/2015
Effective from: 18/08/2015
Decision:
The Director of Environment and Housing agreed to note the content of this report and approve the continued use of the Warrington MBC framework contract for wheeled bins, sacks and other containers through to its expiry in May 2017; (This is to include the plastic sack requirements on behalf of Parks and Countryside and the Locality teams)
In continuing to use the framework, agree to the undertaking of a mini competition exercise inviting those on the framework to submit new bids for the supply of bins, recycling containers and sacks;
Agree that in order to be consistent with the framework conditions the subsequent call-off duration would be applicable from the point of award through to the expiry of the contract, committing ourselves to using the selected provider on an exclusive basis and on the basis of the fixed prices submitted throughout this period ;
Approve the proposed evaluation criteria which would be used to evaluate bids in the mini competition exercise;
Wards affected: (All Wards);
Lead officer: Stephen Holmes
Give authority to incur expenditure of £1,689,010 in respect of 2015/16 Devolved Formula Capital Grant.
Decision Maker: Director of Children's Services
Decision published: 29/07/2015
Effective from: 14/08/2015
Decision:
The Director of Children’s Services agreed to:
· Give authority to incur expenditure of £1,689,010 in respect of 2015/16 Devolved Formula Capital Grant.
· Note that the deadline for implementation is 31st March 2016 and the responsible officer is the Built Environment Programme Manager.
Wards affected: (All Wards);
Lead officer: Stephen Hoggart
To waive Contract Procedure Rules and authorise the use of the Crown Commercial Services Legal Services Framework to procure external legal advice to support the delivery of housing and infrastructure in the East Leeds Extension.
Decision Maker: Director of City Development
Decision published: 28/07/2015
Effective from: 13/08/2015
Decision:
The Director of City Development has agreed to:
a) Waive Contract Procedure Rule 3.1.7, ‘Requirement to use an Approved Framework Agreement’, and approve the use of the Crown Commercial Services Legal Framework to procure strategic and detailed legal advice in support of the programme for delivery of the East Leeds Extension.
b) Waive Contract Procedure Rule 15.2 to reduce the price element of the quality/price evaluation below 40%, to reflect the narrow banding of maximum rates in the CCS Framework and ensure a greater emphasis on securing best value, high quality services through the procurement exercise.
c) Note that the use of the Crown Commercial Service Legal Framework will be subject to the delegated approval of the Chief Officer of PU/PPPU.
Wards affected: Various;
Lead officer: Adam Brannen
Decision Maker: Director of Environment and Housing
Decision published: 28/07/2015
Effective from: 03/08/2015
Decision:
The Director of Environment and Housing has
approved the terms for the acquisition of the properties to be
developed at the subject site.
Appendix 1 to this report has been marked as confidential under
Access to Information Procedure Rules 10.4 (3) on the basis that it
contains information relating to the financial or business affairs
of any particular person (including the authority holding that
information) which, if disclosed to the public, would, or would be
likely to prejudice the commercial interests of that person or of
the Council.
Wards affected: Bramley and Stanningley;
Lead officer: Adrian Dean
Key decision. The level of funding is in excess of £250,000 for each year of the project.
Decision Maker: Director of Environment and Housing
Decision published: 28/07/2015
Effective from: 13/08/2015
Decision:
The Director of Environment and Housing agreed to the approval of the second phase of the Empty Homes Buy Back project. To give authority to spend £9m on the acquisition of properties and the refurbishment programme of works to bring them to the Councils letting standard.
Wards affected: (All Wards);
Lead officer: Richard Marshall
To extend the demolition contract for 12 months from 15th December 2015
Decision Maker: Deputy Chief Executive
Decision published: 27/07/2015
Effective from: 12/07/2015
Decision:
Extension of the ‘Building Demolition Framework Contract’ for 12 months from 15th December 2015
Wards affected: (All Wards);
Lead officer: David Wilkinson
To extend the asbestos removal contract for 12 months from 1st December 2015
Decision Maker: Deputy Chief Executive
Decision published: 27/07/2015
Effective from: 12/08/2015
Decision:
The extend the current contract for a period of 12 months from 1st December
2015
Wards affected: (All Wards);
Lead officer: David Wilkinson
The Director of Environment and Housing is requested to approve the procurement of a new contract to deliver remedial works to block parapets and concrete and structural repairs to 12 high rise Wimpey Nofine blocks (Phase 2).
Decision Maker: Director of Environment and Housing
Decision published: 27/07/2015
Effective from: 12/08/2015
Decision:
The Director of Environment and Housing agreed to approve the procurement of a new contract to deliver remedial works to block parapets and concrete and structural repairs to 12 high rise Wimpey Nofine blocks by utilising the current YORbuild Framework
Wards affected: (All Wards);
Lead officer: Nesreen Lowson
Decision Maker: Director of Children's Services
Decision published: 16/06/2015
Effective from: 04/08/2015
Decision:
The Deputy Director - Learning agreed to waive contract procedure rule 8.1 and 8.2 to award a contract to Mondale IT Solutions Ltd for delivery of effective conference and event management services on behalf of Children's Services traded services. The contract shall commence on 1st July 2015 and will expire on 31st August 2016. The contract will be a call off contract with a maximum contract value of £49,200.
Wards affected: (All Wards);
Lead officer: Helen Stevens