Reference: D41433
Decision Maker: Executive Board
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
a) Authorise programme expenditure and authority to spend from capital scheme number 16585/ASQ/000 to build the Asquith Primary School extension.
b) Note the programme dates identified in this report in relation to the implementation of this decision.
c) Note that officer responsible for implementation is the Project Manager, PPPU.
The Director of Children’s Services submitted a report presenting information and seeking the necessary ‘authority to spend’ in respect of proposals to expand East Ardsley Primary School and Asquith Primary School.
Support for the proposals detailed within the submitted report was received.
RESOLVED –
(a) That expenditure of £884,205 from capital scheme number 16585/ETA/PH3 be authorised, and that the acceptance of variation orders provided by the 10 Schools SPV for costs associated with the construction of the phase III accommodation at East Ardsley Primary School, be approved;
(b) That expenditure of £2,895,100 from capital scheme number 16585/ASQ/000 be authorised and that the acceptance of variation orders provided by the 10 Primaries SPV for costs associated with the construction of the works at Asquith Primary School, be approved;
(c) That the programme dates as identified in section 4.2 of the submitted report in relation to the implementation of these resolutions be noted;
(d) That it be noted that the officer responsible for implementation of such matters is the Project Manager, PPPU;
Reason Key: Expenditure > £250,000;
Wards Affected: Morley North;
Consultees
Executive Board - April 2014
Public Consultation – December 2013
Member briefing at key project stages
Contact: Nigel Wilson, Senior Contract Manager 07891 275570 Email: nigel.wilson@leeds.gov.uk.
Report author: Nigel Wilson
Publication date: 01/08/2014
Date of decision: 25/06/2014
Decided at meeting: 25/06/2014 - Executive Board
Effective from: 05/07/2014