The Deputy Chief Executive submitted a report giving an update on progress towards financial close of the BSF programme.

 

RESOLVED –

(a)  That the contents of the report and progress towards Financial Close be noted together with the decision of the Chair of the Education PFI/ BSF Projects Board to enter into an Early Works Agreement with Interserve Project Services Limited on behalf of the E4L Consortium

(b)  That a revised PFI affordability threshold of £13,148,000 be approved, being the first full year Unitary Charge in 2010/11 to protect the programme against further adverse upward movement in interest rates

(c)  That approval be given to the incurring of additional capital expenditure above the current Capital Programme provision of £30,934,000 amounting to £947,192 on Cockburn and Temple Moor High Schools

 

(This decision was exempt from Call In by reasons of urgency as detailed in paragraphs 2.1 and 2.2 of the report)

 

Publication date: 16/03/2007

Date of decision: 14/03/2007

Decided at meeting: 14/03/2007 - Executive Board