Reference: D54756
Decision Maker: Executive Board
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
This is a proposal for the rebuild of Wetherby High School and its supporting Business Case which seeks to reduce the size of the school site area to release land for housing development which would generate a capital receipt, along with other funding sources including Section 106 and Community Infrastructure Levy.
The Director of Children and Families and the Director of City Development submitted a joint report which set out the current issues regarding the condition of Wetherby High School estate, and following a review undertaken, presented details of proposals regarding the principle of a rebuild of the school.
Members welcomed the proposals and extended their thanks to all of those who had been involved in progressing the proposals to the current position.
In considering this matter, a Member highlighted Royds School, and the investment which it needed. The school’s academy status was acknowledged, and with that in mind it was noted that the options available in respect of taking Royds School forward would be looked into.
Following consideration of Appendix B to the submitted report designated as being exempt from publication under the provisions of Access to Information Procedure Rule 10.4(3), which was considered in private at the conclusion of the public part of the meeting, it was
RESOLVED –
(a) That the principle of the rebuild of Wetherby High School and the ringfencing of capital receipts, CIL and S106, be approved in order to support its delivery, as set out in exempt appendix B (Business Case) to the submitted report;
(b) That following resolution (a) (above), and subject to the successful outcome of the S77 notice and Sport England discussions regarding the release and development of land around Wetherby High School, approval be given to the submission of the planning applications for the school and housing development to support the delivery of a new secondary school at Wetherby for September 2024 at the earliest;
(c) That the principles of the Business Case, set out in the submitted report and exempt appendix B, which has been developed to support the delivery of the proposed rebuild of Wetherby High School, be approved;
(d) That approval be given for the submission of an Executive Board report at a future point in time once the Secretary of State approval to release the land is secured and the details of the Business Case required to deliver the project are known.
Reason Key: Financial Impact>£500K;
Wards Affected: Wetherby;
Portfolio Holder: Executive Member for Economy, Culture and Education
Other reasons / organisations consulted
Executive Member, Ward Members briefings
Consultees
Executive Member for Economy, Culture and Education
Ward Members
Contact: Jane Cash, Senior Project Manager 0113 378 7705 Email: jane.cash@leeds.gov.uk.
Report author: Jane Cash
Publication date: 23/12/2021
Date of decision: 15/12/2021
Decided at meeting: 15/12/2021 - Executive Board
Effective from: 25/12/2021
Accompanying Documents: