Reference: D48075
Decision Maker: Director of Children and Families
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Head of Service Learning Systems agreed
to:
1. Sanction the requirement to enter into an ‘Early
Works’ agreement with the LLEP for ICL to deliver
‘package one’ of the ‘Early Works’
programme necessary to meet the critical path programme for
expansion of Allerton Church of England Primary School. This will
take the form of an ‘Early Works’ agreement between the
authority and Leeds D&B One Ltd for the sum of
£244,057.53.
2. Approve the expenditure of £244,057.53 from capital scheme
number 32655/ACE/EAR for the completion of ‘package
one’ of the ‘Early Works’ programme at Allerton
Church of England Primary School.
3. Note that this constitutes the first of two separate
‘Early Works’ packages required at Allerton Church of
England Primary School prior to entering into formal contract in on
the 7th January 2019. Package one, detailed within this report,
includes for site preparation activities and procurement of key
materials only.
4. Note the programme dates identified in section 4.0 of this
report, in relation to the implementation of this decision,
represents the critical path for project success and must be
adhered to where possible.