Reference: D49952
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways &
Transportation);
i) noted the Executive Board approval on 25th July 2018 for the
expenditure of £11.98m from the LPTIP Capital Programme to
carry out detail design and construction of the Bus Priority
measures and cycling improvements on the route from the Stourton
site into the city centre along Wakefield Road / Low Road / Hunslet
Road;
ii) approved the preliminary design and commencement of detail
design of the proposed Bus Priority measures and cycling
improvements on the route from the M621 J7 (Stourton) roundabout to
Meadow Lane via Wakefield Road, Thwaitegate, Low Road, Hunslet
Road/Lane & Great Wilson Street - as set out in the Drawings
contained within Appendix D;and
iii) approved the expenditure and injection of £205,776
funded from S106 Developer Contributions to be used towards
detailed design and construction of the Wakefield to Leeds A61S Bus
Priority Corridor.
Wards Affected: Hunslet and Riverside;
Contact: Sean Hewitt 0113 3787395 Email: sean.hewitt@leeds.gov.uk.
Publication date: 30/07/2019