Reference: D49953
Decision Maker: Director of Children and Families
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Head of Service Learning Systems agreed
to:
1) Approve the expenditure of £162,005 from capital scheme
number 32737/BGE/SEN for the construction work and associated fees
necessary to facilitate the placement of additional SEN pupils at
the North West SILC and The Richmond Hill Academy under the 2019
SEN ‘Bulge Cohort’ Programme.
Noting that the investment is split as follows:
a. North West SILC – Back Lane Site (10 SEN places
created)
£17,560 from capital scheme number
b. North West SILC – Green Meadows Site (10 SEN places
created)
£18,250 from capital scheme number
c. North West SILC – Penny Fields Site (18 SEN places
created)
£15,306 from capital scheme number
d. The Richmond Hill Academy (6 SEN places created)
£110,889 from capital scheme number
2) Note that the breakdown of project costs, highlighted in point 1
above, are detailed within section 4.4 of this report.
3) Note that the officer responsible for implementation is the Head
of Service Learning Systems.
Wards Affected: Burmantofts and Richmond Hill; Guiseley and Rawdon; Moortown;
Contact: Christopher Gosling, Estate Management - Development Officer 0113 37 87198 Email: christopher.gosling@leeds.gov.uk.
Publication date: 30/07/2019