Reference: D49955
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways &
Transportation):
i) noted the Executive Board approval in June 2017 to progress the
Headrow City Centre Gateway proposals;
ii) noted the Executive Board approval on 17th April 2019 to
progress the Headrow City Centre Gateway to detailed design and
construction;
iii) approved the preliminary design as submitted, of the proposed
Headrow City Centre Gateway project to allow progression to
detailed design and construction;
iv) gave authority to the Development Partner (WSP in the Technical
Assurance Role) and the LPTIP Package Board to approve the
resolution to any issues which may emerge from the Parameters
Schedule. If there is a significant change in scope or deviation
from the Preliminary Design then the new solution may need a
Highways Board decision if there is no general acceptance or
agreement of the solution across LCC departments; and
v) will expect a further Report containing the Traffic Regulation
Orders and further updates on the scheme as a whole as
appropriate.
Wards Affected: Little London and Woodhouse;
Contact: Gwyn Owen, Principal Transport Planner 0113 3787526 Email: gwyn.owen@leeds.gov.uk.