Decision details

Hawksworth Wood Primary School Expansion - Associated Highway Works

Reference: D50040

Decision Maker: Director of City Development

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Chief Officer (Highways & Transportation);
i) noted the contents of the report;

ii) approved the detailed design and implementation of a package of highway works associated with the expansion of Hawksworth Wood Primary school, as shown on the attached drawing no. TM/21/085/01, at a total cost of £75,000;

iii) noted the required expenditure of £75,000, comprising £65,000 works costs, £9,000 staff fees and £1,000 legal fees, all being funded from the Children’s Services Learning Places Capital Programme ( previously approved ); and

iv) gave authority to advertise and introduce a Traffic Regulation Order to introduce waiting restrictions as shown on the attached drawing no. TM/21/085/01 and to advertise a notice under the provision of Section 90c of the Highways Act 1980 associated with traffic calming and if no valid objections are received, to make, seal and implement the Traffic Regulation Order and implement the traffic calming as advertised.

Wards Affected: Kirkstall;

Contact: Nick Borras, Senior Engineer - Traffic Management 0113 3787497 Email: nick.borras@leeds.gov.uk.

Publication date: 02/09/2019