Reference: D50177
Decision Maker: Director of City Development
Is Key decision?: Yes
Is subject to call in?: Yes
Approval to carry out Phase 1 Heritage Maintenance Work at Yeadon Town Hall.
The Chief Officer Asset Management and Regeneration:
a) Gave Authority to Spend of £630,320 from existing budgetary provision, Capital Scheme No. 16996, for maintenance work to Yeadon Town Hall.
b) Approved the appointment of Stone Edge Ltd. as the main contractor to carry out the proposed works to Yeadon Town Hall.
c) Noted the contract value with Stone Edge Ltd. will be £430,210.
Wards Affected: Otley and Yeadon;
Other reasons / organisations consulted
Ward Member briefing notes
Consultees
Relevant Ward Members
Contact: Malcolm Fisher 07891 274515 Email: malcolm.fisher@leeds.gov.uk.
Publication date: 02/10/2019
Date of decision: 10/10/2019
Effective from: 18/10/2019
Accompanying Documents: