The Chief Officer (Highways and
Transportation);
i) noted the principles of the highway works as outlined in Section
3.2 and shown on drawing number 4693-C-D7-07 Rev A; 4693-C-D7-08
Rev A and ITY11326-GA-001 Rev B at Appendix 3 of this report;
ii) gave authority to incur expenditure of £10,000 staff
checking and inspection costs, to be paid by the developer through
the Section 278 Agreement;
iii) gave authority to adopt the land associated with the highway
works including land for footway widening at Scott Lane site
frontage shown shaded yellow on drawing 4693-C-D7-08 Rev A at
Appendix 3 so that it can be added to the Council’s
maintenance regime and instruct Street Registry to update the
Street Register; and
iv) gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980 whereby the associated highway works are
designed and constructed by the developer at their expense, with
the Council checking the design and construction, with step in
rights, should the works not be managed or constructed to
appropriate standard.