Contract Award for Full Fibre Network Programme for Leeds

Reference: D50536

Decision Maker: Director of Resources

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Director for Resources and Housing:
1. Noted that this decision is a direct consequence of implementing previous Key Decision (D48405, dated 13th February 2019) and was in the contemplation of the decision maker at the time the decision was taken; and
2. Approved the award of contract to BT Plc, commencing in March 2020 for a period of 10 years, and with an estimated total value of £20.3M.

Wards Affected: (All Wards);

Contact: Andrew Byrom, Interim Chief Digital and Information Officer 07891 275 241 Email: Andrew.Byrom@leeds.gov.uk.

Publication date: 07/02/2020

Date of decision: 07/02/2020