Reference: D52104
Decision Maker: Director of Children and Families
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Director of Childrens & Families
agreed to:
a) Approve the expenditure of £28,500,000, against the
provisional £28.5m ‘approval to spend’
budget’ provided at the April 2020 Executive Board, from
capital scheme number 32735/000/000 for the redevelopment and
expansion of Benton Park School.
b) Sanction the requirement to enter into a contractual agreement
with D&B One Co. to deliver the Benton Park re-development.
This will take the form of an NEC 3 Option A between the authority
and Leeds D&B One Ltd for the sum of £25,351,599.
c) Authorise acceptance of the tender submitted by the LLEP, via
BAM Construction Limited, in the sum of £25,351,599,
including all contract side design and development fees. Noting
that this figure includes the previously approved sum of
£1,188,101 for the completion of the necessary ‘Early
Works’ package (DDN D50877).
d) Note that the approval sum detailed in point (a) above is
inclusive of the following elements; £25,351,599 for the
construction contract, £1,850,785 for professional services
including the project technical assurance function and NEC 3
Project manager, £621,747 for Highways and Authority works,
£343,719 for site decant and mobilisation risk, £60,000
for furniture & equipment to support the expansion,
£111,321 for surveys and planning fees, £113,610 for
internal services and fees, £47,219 for the performance bond.
A client held contingency, commensurate with a project of this
value, has been included within the approval figure to address any
risks that occur during construction.
e) Note the programme dates identified in section 3.2 of this
report, in relation to the implementation of this decision,
represents the critical path for project success and must be
adhered to where possible.
f) Note that the officer responsible for implementation is the Head
of Service Learning Systems.