Reference: D52186
Decision Maker: Director of Children and Families
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Head of Service Learning Systems agreed
to:
a) Sanction the requirement to enter into an ‘Early
Works’ agreement with the LLEP for Galliford Try PLC to
deliver the second package of the ‘Early Works’
programme necessary to meet the critical path programme for
construction of the East Leeds Free School. This will take the form
of an ‘Early Works’ agreement between the authority and
Leeds D&B One Ltd for the sum of £498,890.
b) Approve the expenditure of £498,890 from capital scheme
number 33177 / EAS / 000 for the completion of the ‘Early
Works’ programme at East Leeds Free School.
c) Note the programme dates identified in section 3.2 of this
report, in relation to the implementation of this decision,
represents the critical path for project success and must be
adhered to where possible.
Wards Affected: Guiseley and Rawdon;
Contact: Christopher Gosling, Estate Management - Development Officer 07891 276 855 Email: christopher.gosling@leeds.gov.uk.
Publication date: 10/08/2020
Accompanying Documents: