The Chief Officer, Highways &
Transportation;
i) Noted and approved the final layout of the Cottingley Hall
Estate – Public Transport Infrastructure Improvement scheme
as shown on the attached Drawing No TM/25/1/321/GA-2A;
ii) Gave authority to issue the works to the term contractor and to
construct the scheme as shown.
iii) Noted the required expenditure of £647,000, comprising
£510,000 works costs, £50,000 Statutory Undertakers
diversionary costs, £86,000 staff fees and £1,000 legal
fees, all being funded from the Connecting Leeds programme as
previously approved by Executive Board and the Combined
Authority’s Project Assurance Team.
iv) Noted that the scheme, valued at £647,000, is to be
wholly funded from West Yorkshire Combined Authority’s
Connecting Leeds programme as previously approved by Executive
Board.
v) Gave authority to advertise and introduce a Traffic Regulation
and Movement Order to introduce waiting restrictions and bus lane
respectively as shown on the attached drawing no. TM/25/1/321/GA-2A
and if no valid objections are received, to make, seal and
implement the Traffic Regulation and Movement Orders, as
advertised; and
vi) Authorised the City Solicitor to advertise draft Traffic
Regulation and Movement Orders and if no valid objections are
received, to make, seal and implement the Orders and pedestrian
crossings as advertised
Wards Affected: Beeston and Holbeck;