Decision details

Approval to award a construction contract for repair and improvement works to the Appletons and Saville Green high rise housing blocks.

Reference: D52892

Decision Maker: Director of Resources

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Director of Resources and Housing:
a) approved the award of the construction contract for repair and improvement works to the high rise housing blocks at Appletons and Saville Green to Kier Services Limited in the sum of £4,004,055.80.
b) noted that it is estimated construction will start on site May 2021 and last for twelve months.

Wards Affected: Burmantofts and Richmond Hill;

Contact: Louise Almond 07712 214953 Email: Louise.Almond@leeds.gov.uk.

Publication date: 18/03/2021

Accompanying Documents: