Reference: D52896
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
a) noted the detail of the highway works as outlined in section 3
of this report and shown on plan ref: SCP/190274/F13 Rev B attached
at Appendix 3 of this report;
b) gave authority to negotiate the terms of and enter into an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by the developer and overseen by the
Council; and
c) gave authority to incur expenditure of £5,000 staff
checking and inspection fees to be fully funded by a developer
through a Section 278 Agreement.
Wards Affected: Adel and Wharfedale;
Contact: Gurnam Shergill, Highways Engineer 0113 378 2235 Email: gurnam.shergill@leeds.gov.uk.