Decision details

Council House Growth Programme: Approval to enter into separate Construction Contracts to deliver new build council homes at Meynell Approach, Holbeck and Silk Mill Drive, Tinshill; and authority to spend

Reference: D54134

Decision Maker: Director of City Development

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Director of City Development granted approval to enter into separate NEC4 Engineering and Construction Contracts (Option A) with United Living (North) Ltd, for the construction of 28 new build council homes at Meynell Approach for the sum of £5,035,468.14 and 2 new build council homes at Silk Mill Drive for the sum of £505,037.79 giving a total cost of £5,540,505.93; enabling a contract start date of 28th May 2021, a site access date of 5th July 2021 and a completion date of 14th April 2022; and approval to spend.

Wards Affected: Beeston and Holbeck; Weetwood;

Contact: Sarah Griffiths 3787703.

Publication date: 28/05/2021