Design Cost Report for the Learning Places Programme ‘bulge’ cohort project at Horsforth School

Reference: D54215

Decision Maker: Director of Children and Families

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Head of Service Learning Systems agreed to:
a) Authorise expenditure of £394,316.45 from capital scheme number 33177/BGE/HOR to facilitate the construction project necessary to deliver the placement of a ‘bulge’ cohort at Horsforth School.
b) Authorise acceptance of the tender submitted by Portakabin Ltd. for the sum of £306,834.17. This figure is inclusive of all design fees, development costs and surveys.
c) Note the programme dates identified in section 30 of this report in relation to the implementation of this decision. The final delivery date for this scheme is prior to the commencement of term September 2021.
d) Note that the officer responsible for implementation is the Built Environment Principal Development Officer.

Wards Affected: Horsforth;

Contact: Christopher Gosling, Estate Management - Development Officer 07891 276 855 Email: christopher.gosling@leeds.gov.uk.

Publication date: 24/06/2021