a) The Chief Officer Highways and
Transportation approved entering a Funding Agreement, for Element
B2 of the WY UTMC project, with West Yorkshire Combined Authority
for the sum of £917,000.
b) In order to deliver the main component of Element B2 of the WY
UTMC project, the Chief Officer Highways and Transportation
approved the award of the West Yorkshire Hosted UTMC contract to
Dynniq UK Ltd in the sum of £551,662.18, for an initial
period of 4 years and with the facility to extend the contract up
to a further four years.
c) The Chief Officer (Highways & Transportation) gave authority
to inject £917,000 into the Highways Capital programme funded
by pre-approved WYCA (West Yorkshire Combined Authority) grant
funding.
d) The Chief Officer (Highways & Transportation) gave authority
to spend the funding of £917,000 on the approved West
Yorkshire UTMC system and associated items of Element B2 of the WY
UTMC project, funded by WYCA.