Decision details

Award of the design and build contract to deliver new build extra care and general needs housing schemes at Cartmell Drive South and Middlecross

Reference: D54600

Decision Maker: Director of City Development

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The authority to award has previously been approved however the fees were to be confirmed at a later date – this report outlines the total PSC cost as follows:
Total = £788,282.55

Wards Affected: Armley; Temple Newsam;

Contact: Tanya Gilston, Housing Growth Officer 0113 3781927 Email: tanya.gilston@leeds.gov.uk.

Publication date: 26/10/2021