The Head of Civil Engineering & Infrastructure:

a) Noted the FDGiA £658k and £50k funding levy secured together with the Section 106 £300k giving total available funding of £1,058.0k to implement a flood alleviation scheme at Farnley Wood Beck and noted the previous injection and authority to spend £450k approved in February 2021.
b) Injected and gave authority to incur further expenditure of £421,500 to fully implement the flood alleviation scheme at Farnley Wood Beck.



Wards Affected: Beeston and Holbeck;

Contact: Ian McCall, Flood Risk Engineer 0113 378 8012 Email: Ian.McCall@leeds.gov.uk.