The Director of Communities, Housing and Environment is asked to approve the procurement and implementation of a new contract to undertake re-roofing works for a sheltered housing complex in Garforth, Halliday Court.

 

Decision:

The Director of Communities, Housing and Environment

a)  Approved the Authority to Procure the proposed procurement strategy in line with CPR 3.1.7 to source an external contractor to deliver the re-roofing works following competitive procedure utilising and inviting specialist roofing contractors from Constructionline following an expression of interest which provided a list of 9 interested contractors. It should be noted that all contractors invited to tender will be fully vetted by the Council prior to contract award in order for it to satisfy itself that the contractors demonstrate their technical and financial ability and capacity to deliver this scheme.

b)  Approved the Authority to Spend of £650,000 for construction to undertake and complete the required re-roofing works at Halliday Court, as referred to in paragraph 13 of the report.

 

Reason Key: Financial Impact>£500K;

Wards Affected: Garforth and Swillington;

Other reasons / organisations consulted

Local ward members and tenants within the complex will be engaged and consulted in relation to the planned works.

Contact: Paul Rounding, Capital Programme Manager 07891 272386 Email: Paul.Rounding@leeds.gov.uk.