Highways Infrastructure Maintenance Programmes (Structures) 2023/24

Reference: D56251

Decision Maker: Director of City Development

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

To seek authority to incur expenditure to the limit of the available budget and to add the schemes shown in the Appendices B to this report to the Highways Infrastructure Maintenance Programmes (Structures) 2023/24.

Decision:

The Chief Officer (Highways and Transportation);

a)  gave authority to incur expenditure of £6,205,088 (£5,104,325 works costs, £900,763 internal staff, and £200,000 engineering partner fees) funded from the 2023/24 City Region Sustainable Transport Settlement (£4,205,088) and Leeds City Council Capital Resources (£2,000,000); and,

b)  approved the addition of the schemes listed in Appendix B to this report into the Highways Infrastructure Maintenance Programmes (Structures) 2023/24.

Reason Key: Financial Impact>£500K;

Wards Affected: (All Wards);

Other reasons / organisations consulted

Internal consultation

Consultees

Executive Member for Infrastructure and Climate

Contact: Babak Ahmadian, Bridges Manager 0113 378 7353 Email: babak.ahmadian@leeds.gov.uk.

Publication date: 04/04/2023

Date of decision: 14/04/2023