Reference: D56757
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation) was requested to:
1. Approve commencement of the TRO process required for the
additional fasttrack sites added to phase 1.1a, noting that future
elements of phase 1 will require a separate TRO. Fasttrack sites
are listed below.
2. Give authority to request the City Solicitor to advertise any
Traffic Regulation Orders (Parking Places Order, Waiting
Restriction Order or Experimental Order) as required to address/
resolve the problems identified for each site, and if no valid
objections are received, to make, seal and implement the Orders as
advertised.
3. Note that delivery of the docks to meet the 15th September
launch date will not give sufficient time for making of the orders
and delivery of signing and lining to support the TRO’s. This
will follow on.
Wards Affected: Beeston and Holbeck; Chapel Allerton; Headingley and Hyde Park; Hunslet and Riverside; Little London and Woodhouse; Weetwood;
Contact: Gillian Macleod, Highways Development Officer 0113 398 8091 Email: gillian.macleod@leeds.gov.uk.
Publication date: 07/09/2023
Accompanying Documents: