Decision details

Design Cost Report for fees associated with the expansion of Leeds City Academy

Reference: D57134

Decision Maker: Director of Children and Families

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Head of Learning Systems agreed to:
• Incur costs of £228,949.13 associated with the Pre-Construction Services Agreement from capital scheme number 33471/LCA/000.
• Incur costs of £78,789 associated with RIBA stage 4 fees.
• Note the programme dates identified at point 9 of this report require a decision at the earliest opportunity to enable detailed design work to continue and for the project to remain on programme.

Wards Affected: Headingley and Hyde Park;

Contact: Adele Robinson, Principal Development Officer, Built Environment 07891 276856 Email: adele.robinson@leeds.gov.uk.

Publication date: 07/02/2024