Reference: D47494
Decision Maker: Director of Children and Families
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Director of Childrens & Families
agreed to:
1. Approve the expenditure of £3,000,000 from capital scheme
number 32450/BEE/000 for the expansion of Beecroft Primary School.
This figure is inclusive of all construction costs, professional
services, necessary supporting costs and a client held contingency
commensurate with a project of this scale and complexity. This is
to be funded from the combined £3m allocated to the expansion
of Beecroft Primary approved at the December 2016 (DDN D43998) and
February 2018 (DDN D46256) Executive Boards.
2. Note that the figure detailed above is includes £868,416
of previous approvals required to facilitate the ‘Early
Works’ package (DDN D46271).
3. Sanction the requirement to enter into a contractual agreement
with the LLEP for ICL to deliver the expansion at Beecroft Primary
School. This will take the form of a 2016 JCT Design & Build
contact between the authority and Leeds D&B One Ltd for the sum
of £2,522,512. For contractual purposes this figure includes
previous approvals, totalling £868,416, required to
facilitate the ‘Early Works’ package.
4. Authorise acceptance of the tender submitted by the LLEP in the
sum of £2,522,512.40, including all design and development
fees but exclusive of LLEP management and consultant fees.
Wards Affected: Kirkstall;
Contact: Edward Staveley, Principal Asset Management Officer , City Development 0113 37 87204 Email: edward.staveley@leeds.gov.uk.
Publication date: 19/04/2018