Reference: D48100
Decision Maker: Director of City Development
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
The Chief Officer (Highways and
Transportation):
i) noted the principles of the highway works as outlined in Section
6.2 and shown indicatively on Drawing Numbers 7409 100 Rev C3 and
TDS2018-1B;
ii) noted the principle of loading and/or waiting restrictions
shown indicatively on Drawing Number TDS2018-1B which will be
developed at detail design stage and which will be the subject of a
further report;
iii) approved the adoption of new highway construction on land
shaded red on drawing number 7409 100 Rev C3 so that it can be
added to the Council’s maintenance regime;
iv) gave authority to negotiate the terms of, and enter into, an
agreement with the developer under the provisions of Section 278 of
the Highways Act 1980; whereby the works associated with the
development are carried out by this Council at the cost of the
developer;
v) gave authority to incur expenditure of £35,000 works costs
and £15,000 staff costs and meet the costs of any other works
resulting from the outcome of Safety Audits and consultations, all
to be fully funded by a developer through a Section 278 Agreement;
and
vi) gave authority to carry out the detailed design, tender and
implement the works as set out in Section 6.2.
Wards Affected: Cross Gates and Whinmoor;
Contact: Adrian Hodgson 0113 378 8088 Email: adrian.hodgson@leeds.gov.uk.
Publication date: 05/11/2018
Accompanying Documents: