The Chief Officer (Highways and Transportation):
a) a) Noted the detail of the highway works provided in paragraph 1 of this report and as shown on the plan included at Appendix 3 of this report;
b)
c) b) Gave authority to negotiate the terms of and enter into an agreement with the developers under the provisions of Section 278 of the Highways Act 1980; whereby the works associated with the development are carried out by the developer at the developer’s expense under Leeds City Council’s supervision;
d)
e) c) Gave authority to incur capital expenditure of £5,000 staff costs, all to be fully rechargeable to the developer through the Minor Section 278 Agreement. These are subject to estimated costs; and
f)
g) d) Approved the adoption of new highway construction on land hatched in magenta on drawing number Y622 - BPL - 00 - XX - DR - C - 0004 P3 so that it can be added to the Council’s maintenance regime.