Decision details

The Vine SEN college, Torre Drive, Burmantofts Off-site Highway Works

Reference: D55567

Decision Maker: Director of City Development

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

The Chief Officer Highways and Transportation;

a. Noted the content of this report;

b. Approved the detailed design and implementation of a package of highway works associated with the construction of The Vine SEN College on Torre Drive, as shown on drawing no. 1046-LCC-07-XX-DR-TM-01_02, which is attached as Appendix A;

c. Authorised the total expenditure of £50,000, comprising £39,000 works costs, £10,000 staff fees and £1,000 legal fees, which is to be fully funded from the Children’s Services Learning Places Capital Programme (previously approved under 33177/LAU/000);

d. Instructed the City Solicitor to advertise a Traffic Regulation Order to introduce waiting restrictions as shown on the attached drawing no. 1046-LCC-07-XX-DR-TM-TRO-01 (Appendix B) and to advertise notices under the provision of s90C of the Highways Act 1980 associated with the introduction of a traffic calming feature.

e. If no valid objections are received, instructed the City Solicitor to subsequently make, seal and implement the Traffic Regulation Order and implement the traffic calming feature utilising the powers under s90C of the Highways Act 1980 all as advertised.

Wards Affected: Burmantofts and Richmond Hill;

Contact: Joshua Freeman, Traffic Technician 0113 3368155 Email: Joshua.Freeman@leeds.gov.uk.

Publication date: 16/08/2022