Reference: D56318
Decision Maker: Director of City Development
Is Key decision?: Yes
Is subject to call in?: Yes
Approval of schemes to deliver traffic signal upgrades across the road network including asset renewal, control strategy upgrades, telecommunications infrastructure upgrades and optimisation of existing assets.
The Chief Officer (Highways and Transportation) has:
i) Reviewed and approved the prioritised list of proposed schemes set out in Appendix A for delivery as part of the 2023/24 Urban Traffic Management & Control (UTMC) Capital Programme.
ii) Given authority to incur expenditure of an expected £2,113,734 (inclusive of all works costs, fees and legal costs) which will be funded by way of £2,073,000 from the City Region Sustainable Transport Settlement (CRSTS) and £40,734 from a S106 developer contribution.
iii) Approved the injection of £2,073,000 from the CRSTS and £40,734 for the A63/Lidgett Lane junction from a S106 developer contribution into the UTMC Capital Programme 2023/24.
Reason Key: Financial Impact>£500K;
Wards Affected: Alwoodley; Armley; Bramley and Stanningley; Burmantofts and Richmond Hill; Chapel Allerton; Garforth and Swillington; Gipton and Harehills; Hunslet and Riverside; Killingbeck and Seacroft; Kippax and Methley; Kirkstall; Little London and Woodhouse; Moortown; Roundhay; Temple Newsam;
Other reasons / organisations consulted
Member briefings
Consultees
Executive Member for Infrastructure and Climate
Engagement with the Ward Members will be undertaken prior to individual schemes commencing.
Contact: Joel Dodsworth, UTMC Manager Highways 0113 378 8128 Email: joel.dodsworth@leeds.gov.uk.
Publication date: 28/04/2023
Date of decision: 10/05/2023
Effective from: 18/05/2023
Accompanying Documents: