135 Connecting Leeds: A58 Beckett Street Bus Priority Corridor PDF 185 KB
To consider the report of the Director of City Development providing an update on the progress of significant schemes which have made up the Connecting Leeds programme during 2019/20 and provides details regarding the proposal to establish a bus priority corridor on the A58, Beckett Street.
Additional documents:
Minutes:
The Director of City Development submitted a report providing an update on the progress of significant schemes which have made up the ‘Connecting Leeds’ programme during 2019/20 and which provided details regarding the proposal to establish a bus priority corridor on the A58, Beckett Street.
It was noted that local Ward Councillors were supportive of the proposals detailed within the submitted report.
RESOLVED –
(a) That the progress which has been made since April 2016 in developing proposals for the relevant projects benefiting from ‘Connecting Leeds’ funding, together with the subsequent public consultation responses, be noted;
(b) That the injection of £14.3m Department for Transport (DfT) funding into the Bus Infrastructure programme transferred from the Rail and Bus packages delivered by the West Yorkshire Combined Authority, be approved, with the potential for future transfers of DfT funding from the Rail and Bus packages being noted, which would be subject to their deliverability within the timescales set by the DfT;
(c) That the expenditure of £14.54m from the ‘Connecting Leeds’ Capital Programme to carry out detail design and construction of the A58 Beckett Street including York Street, be authorised;
(d) That the injections of S106 Developer contributions of £431,375 for the A58 Beckett Street scheme including York Street, be approved;
(e) That subject to ongoing consultation with the Executive Member as appropriate, it be noted that the Chief Officer, Highways and Transportation will approve the final version of the designs for construction.