77 WykeBECC (Built Environment and Catalyst Centre) - Seacroft PDF 95 KB
To consider the joint report of the Director of City Development and Director of Environment and Neighbourhoods on a proposal to establish a Wyke Built Environment and Catalyst Centre on the site of the East Leeds Family Learning Centre and seeking to inject £1,295,000 into the City development capital programme from the Local enterprise Growth Initiative programme to cover the expenditure.
Minutes:
The Director of City Development and Director of Environment and Neighbourhoods submitted a joint report on a proposal to establish a Wyke Built Environment and Catalyst Centre on the site of the East Leeds Family Learning Centre and seeking to inject £1,295,000 into the City Development capital programme from the Local Enterprise Growth Initiative programme to cover the expenditure.
RESOLVED –
(a) That an injection of an additional £1,295,000 into the City Development capital programme from the existing £15,600,000 LEGI programme be approved.
(b) That the scheme as detailed in the report, at an estimated total cost of £1,295,000 be approved.
(c) That the incurring of expenditure of £1,295,000 towards the purchase of the modular building, site preparation, fit out costs and associated fees to be met from the LEGI be authorised.