Woodhouse Lane Multi Storey Car Park

Meeting: 13/10/2010 - Executive Board (Item 87)

87 Design and Cost Report: Proposed Works at Woodhouse Lane Multi Storey Car Park pdf icon PDF 103 KB

To consider the report of the Acting Director of City Development outlining a proposed design and cost freeze at RIBA Stage D for the proposed improvement and backlog maintenance works to the Woodhouse Lane Multi Storey Car Park and seeking authorisation of related expenditure and letting of contracts.

 

Minutes:

The Acting Director of City Development submitted a report regarding a design and cost freeze at RIBA Stage D on the proposed improvement and backlog maintenance works to the Woodhouse Lane Multi Storey Car Park. In addition, the report also sought authorisation to the incurring of related expenditure and letting of related contracts.

 

RESOLVED –

(a)  That the design and cost freeze at RIBA Stage D for the proposed improvement and backlog maintenance works to the Woodhouse Lane Multi Storey Car Park be approved.

 

(b)  That subject to the tender sum for the proposed works being within the budget available, approval be given to the letting of the contract and the incurring of expenditure of £5,806,500 from existing budget provision (Capital Scheme No 13307/WHL/000) on the proposed design and subsequent improvement and backlog maintenance works to the Woodhouse Lane Multi Storey Car Park.