To consider the report of the Assistant Chief Executive (Citizens and Communities) providing an update on the delivery of Phase 1 of the Transactional Web Services project. In addition, the report seeks approval of a £4,866,000 injection into the Capital Programme, whilst also seeking authority for the Assistant Chief Executive (Citizens and Communities) to spend in order to deliver the second phase of the Transactional Web Services project.
Additional documents:
Minutes:
Further to Minute No. 260, 16th May 2012, the Assistant Chief Executive (Citizens and Communities) submitted a report providing an update on the delivery of Phase 1 of the Transactional Web Services project. In addition, the report sought approval of a £4,866,000 injection into the Capital Programme, whilst it also sought authority for the Assistant Chief Executive (Citizens and Communities) to spend in order to deliver the second phase of the Transactional Web Services project.
RESOLVED –
(a) That the progress made on the delivery of Phase 1 of the Transactional Web Services project, be noted;
(b) That an injection of £4,866,000 into the Capital Programme be approved and that the Assistant Chief Executive (Citizens and Communities) be provided with the necessary authority to spend in order to deliver the second phase of the Transactional Web Services project, as detailed within the submitted report.