Issue - meetings

2017 Learning Places Expansion - Cockburn School - Proposed hall expansion

Meeting: 19/04/2017 - Executive Board (Item 185)

185 Approval to Spend for the Learning Places Expansion Project at Cockburn School pdf icon PDF 135 KB

To consider the report of the Director of Children and Families providing details of a proposal brought forward to meet the Local Authority’s duty to ensure sufficiency of school places, and which supports the achievement of the Best Council priorities to improve educational achievement and close achievement gaps.  Specifically, this report seeks ‘Approval to Spend’ for the high level budget, as detailed, to deliver an expansion project at Cockburn (Academy) School in order to accommodate an increase in the Published Admission Number from 210 to 240 from September 2018, including a ‘bulge’ cohort of 60 additional pupils from September 2017.

 

Additional documents:

Minutes:

The Director of Children and Families submitted a report providing details of a proposal brought forward to meet the Local Authority’s duty to ensure sufficiency of school places, and which supported the achievement of the Best Council priorities to improve educational achievement and close achievement gaps. Specifically, the submitted report sought the relevant ‘Approval to Spend’ in order to deliver an expansion project at Cockburn (Academy) School to accommodate an increase in the Published Admission Number (PAN) from 210 to 240 from September 2018, including a ‘bulge’ cohort of 60 additional pupils from September 2017.

 

RESOLVED –

(a)  That Capital expenditure of £1,559,624 to support the increase in PAN at Cockburn School, be authorised, with it being noted that this figure is the maximum project budget and encompasses all works associated with this scheme;

 

(b)  That the programme dates, as identified within section 4.0 of the submitted report, regarding the implementation of this decision, be noted, with it also being noted that the final delivery date for this scheme is prior to the commencement of term September 2017;

 

(c)  That the necessary authorisation be provided to enter into a grant agreement with Cockburn Multi-Academy Trust for the sum of £1,559,624, with the terms of the agreement being approved by the Director of Children and Families, under his existing delegated authority;

 

(d)  That it be noted that the officer responsible for the implementation of such matters is the Head of Learning Systems.