To consider a report of the Chief Planning Officer on an application for engineering works to form flood storage area
(report attached)
Minutes:
Plans and photographs were displayed at the meeting. A Members site visit had taken place earlier in the day
The Panel’s Lead Officer provided a brief history of the site, for Members’ information
The Panel was informed that outline planning permission was granted in 1997 for the erection of 6 houses. The Reserved Matters application was however refused on issues relating to design and that the scheme did not take flooding into account. The applicant lodged an appeal and planning permission was subsequently granted by the Inspector . A S106 agreement was entered into which stated that provision would be made to address the flooding before commencement of the development, with this being accepted by the Inspector
In 2006, a flood compensation scheme was submitted which the Environment Agency (EA) in January 2007, did not object to. In July 2007, a severe flooding event occurred which resulted in the EA revising their position, stating that the proposed scheme was not fit for purpose. Since that time until recently, the EA’s concerns were maintained and discussions to resolve the situation had been ongoing
In 2008, the developer commenced laying out the foundations for a garage block on the site but was informed that work must stop as this was in breach of the S106 agreement. The developer complied with this request but the works which had been carried out on site meant that the planning permission remained live, with this being checked with Legal Services
Having been provided with contextual information in respect of the application, Officers then presented the report to Panel which sought approval for a flood compensation storage area relating to an approved residential development which was located in the functional floodplain (Zone 3b)
The proposals were to raise the properties by 50cm and displace the water towards the floodplain area – Keswick Beck. A cut and fill operation would be used, with the materials excavated being used to create a bund of up to 1.5m high, which, as well as being requested by the EA, would also provide a greater degree of comfort to the residents in the area. Outlet pipes would be placed in the bund and whilst local concerns had been raised about the sewer which crossed the site, Members were informed that the sewer would not be impacted on
To ensure the bund did not create more flooding, an agreement had been obtained with two adjacent landowners that their land could be flooded if a 1:100 year flood event occurred
In respect of the EA, it was now satisfied that the proposed scheme was acceptable, as was Yorkshire Water and the Council’s Flood Risk Manager
Whilst there had been a significant level of objections received to the scheme proposed in 2009, since the revised scheme which was before Members had been advertised, it was reported that no representations had been received
Members commented on the following matters:
Officers provided the following responses:
RESOLVED - To defer and delegate approval to the Chief Planning
Officer, subject to the conditions set out in the submitted report and following completion of a Section 106 Agreement to cover the following matter:
In the circumstances where the Section 106 has not been completed within 3 months of the resolution to grant planning permission, the final determination of the application shall be delegated to the Chief Planning Officer
Supporting documents: