To receive and consider a presentation from the Chief Officer, Climate, Energy and Green Spaces on the proposals for Heat Network Zoning contained in the Energy Act and the implications for the city.
Minutes:
The report of the Chief Officer, Climate, Energy and Green Spaces provided an introduction to a presentation on the proposals for Heat Network Zoning contained in the Energy Act and the implications for the city.
George Munson, Senior Project Manager, outlined the following information to Members:
· Heat Network Zoning was Government policy, as part of the Energy Act 2023, designed to support district heating network growth in areas identified to deliver lower cost decarbonisation than heat pumps. The detailed policy was at a consultation stage, closing at the end of February 2024, and was expected to be fully implemented by 2025.
· The policy mandated that larger buildings and new developments were connected to district heating, with Local Authorities becoming Zoning Coordinators, holding a coordination, liaison and enforcement role. Zoning Coordinators were to issue tenders for heat network delivery bodies that build networks and connect customers.
· Potential zoning areas, where criteria for district heating to be lower cost than heat pumps had been met, had been identified for Leeds via a Heat Network Zoning Pilot. The Advanced Zoning Delivery Programme (AZP) had consolidated data for potential sites and focused on the city centre and Aire Valley zones, existing Leeds Pipes network zonal expansion, Skelton Grange energy from waste site, as well as additional areas of interest.
· Work had been conducted to understand the extent and scope of the policy in Leeds, with an estimated 650 gigawatts per year of mandatable building heat loads, 175km length of pipe network, a zone demand of 1,439 gigawatts per year of zone demand and a capital investment of £650 million.
· The AZP was a Government sponsored programme and Leeds had chosen to focus this on the city centre, Aire Valley and Southbank area to understand the cost of strategic oversizing of elements of the network. The Green Heat Network funding application for a network in the Southbank area was to form the base case.
· Early stages of the AZP project had identified the Southbank network was required to be three times larger than initially planned to provide capacity for mandated buildings.
· The key points of the consultation were noted as understanding the role and requirements to perform as a Zoning Coordinator, acting as a local regulator, establishing and procuring zone networks, running competitions to secure delivery bodies, as well as an enforcement, liaison and review role, including internal appeals. Funding was to be initially central, with support from the Central Zoning Authority.
· The key issues identified for the Zoning Coordinator model were similarities to the planning authority, unclear levels of funding required and delivery capabilities, the proposed governance process, and the implication of appeals and liability of the Council.
· The impacts on existing networks were to avoid the need to sell network output to delivery bodies with an incumbent rule proposed, gifting rights to existing network operations, outside of incumbent areas competition for delivery bodies was held. If the Council was to become a delivery body, it was required to establish a separate Zoning Coordinator entity.
· For inoperable areas, outside or on the fringes of network heating zones, Officers were minded to render these zones unviable and allow Zoning Coordinators powers to designate the areas as separate zones, as part of the consultation response.
· Issues that may impact existing networks were outlined as setting up a Zoning Coordinator as a separate body outside the Council may be undemocratic; the planning authority was recommended as an appropriate vehicle for zone coordination. Also, if a district heating contractor was already competitively procured, it was anticipated to satisfy requirements of the Utilities Act 2023.
· The following recommended consultation responses were outlined, as part of zoning development, coordinators should reserve the right to engage with mandated buildings and heat sources and hold a stronger position to refine recommended zones from the Central Authority. A longer statuary consultation period prior to zone establishment than the proposed 21 days, a loan facility with deferred repayments for delivery bodies to account for the significant investment need ahead of revenue generation and a consistent approach to carbon standards to avoid a preference for air source heat pumps.
· The policy was considered to be overall good, and a response was to be submitted by the end of February 2024.
During the discussions the following matters were considered:
RECCOMENDED –
a) That the report, along with Members comments, be noted.
b) That the intention for the Chief Officer, Climate, Energy and Green Spaces to respond to the consultation on behalf of the Council in consultation with the Chair of the Climate Emergency Advisory Committee, be noted.
Supporting documents: