Issue - decisions

S106 Highways works associated with residential Development resulting from the redevelopment of the former DWP site and Bodington Hall site Otley Road, Adel, Leeds – Adel Lane Phase 2 Traffic Calming & A6120 Cycle Route Improvement

09/07/2019 - S106 Highways works associated with residential Development resulting from the redevelopment of the former DWP site and Bodington Hall site Otley Road, Adel, Leeds – Adel Lane Phase 2 Traffic Calming & A6120 Cycle Route Improvement

The Chief Officer (Highways & Transportation);
i) noted the contents of this report,

ii) gave authority to progress the detailed design and implement the highway works as shown on drawing no. 732852/LCC/HWT/XX/DR/EP/MI_06_;

iii) gave authority to advertise a Notice under the provisions of Section 90C of the Highways Act 1980 required for each proposed vertical deflection traffic calming feature;

iv) gave authority to incur expenditure of £73,716 being £40,716 works costs, £27,000 staff fees, and £6,000 legal fees, fully funded by Section 106 receipts; and

v) approved with reference to the powers contained in Section 66(4) of the Highways Act 1980, that the relevant length of footway on Ring Road Adel shown on drawing 732852/LCC/HWT/XX/DR/EP/MI_06_ as existing shared cycle footway are removed and that following the removal of the footways, cycle tracks are constructed under the powers contained under the provisions of section 65(1) of the Highways Act 1980 for shared joint use by pedal cyclists and pedestrians.