Tender evaluation results and proposed award of contract for repair and improvement works to the Appletons and Saville Green high rise housing blocks

15/08/2019 - Tender evaluation results and proposed award of contract for repair and improvement works to the Appletons and Saville Green high rise housing blocks

The Director of Resources and Housing:
a) approved the award of the Design Services Agreement contract for repair and improvement works to the Appletons and Saville Green high rise housing blocks to Kier Services Limited for the sum of £252,998.27. This initial sum will cover the DSA contract stage, where the construction design and costs will be developed.
b) noted that it is estimated construction will start on site July 2020 and last for 14 months. The estimated total contract value is £4million.
c) recognised that Appendix 1 should be designated as exempt from publication