Contract and financial decisions to deliver the ERDF funded Transformational Insulation in Back to Backs project

08/10/2019 - Contract and financial decisions to deliver the ERDF funded Transformational Insulation in Back to Backs project

The Director of Resources and Housing:

a)  Gave authority to enter into an ERDF grant agreement for £5,256,713 for the TIBB programme;

b)  Approved the request to inject  £5,256,713 of ERDF grant funding into the Housing Leeds Capital Programme with match funding of £5,068,759 provided from the non-traditional and hard to treat budget within the approved Housing Revenue Account Capital Programme;

c)  Gave authority to spend for £10,137,519 to deliver the entire TIBB programme;

d)  Gave authority to procure a contractor to deliver this work from an approved framework.