Hovingham Primary School Expansion – Associated Highway Works

02/09/2019 - Hovingham Primary School Expansion – Associated Highway Works

The Chief Officer (Highways & Transportation);
i) noted the contents of the report;
ii) approved the detailed design and implementation of a pedestrian crossing (zebra) facility on Hovingham Avenue in Harehills, associated with the planning approval granted for the Hovingham Primary School expansion, as shown on the attached drawing no. TM/13/082/01, at a total cost of £15,000;
iii) noted the required expenditure of £15,000, comprising £13,000 works costs, £2,000 staff and legal fees, all being funded from the Children’s Services Learning Places Capital Programme ( previously approved); and
iv) gave authority to advertise a notice under the provision of Section 23 of the Highways Act 1980 associated with the provision of a formal pedestrian crossing facility and if no valid objections are received, to implement the works as advertised.