Professional Services Contract with Balfour Beatty for Technical Design Services for the Transforming Cities Fund

30/09/2020 - Technical Design Services for the Transforming Cities Fund

The Director of City Development:

a) Gave authority to spend £3,681,036 fees associated with the completion of RIBA Stage 4, noting that this includes fees for Balfour Beatty, Steers, Network Rail and Corderoy.

b) Approved the injection of Transforming Cities Fund (TCF) development funding of £1,984,932 into the capital programme and a further £3,104,572 once approved by Investment Committee on the 7th October 2020.

c) Approved the council entering into the Pre-Construction Order, ensuring the project progresses to the next phase in the Scape process.

d) Authorised Balfour Beatty to provide detailed design services (subject to the terms set out in this report) to develop the project to construction.

e) Approved the extension of the Basic Asset Protection Agreement to cover RIBA 4 design activities